Fwd: Some Problem with Auto Rescheduling

Mark Eisenblaetter mark.eisenblaetter at gmail.com
Fri Nov 16 10:54:21 CET 2007


Hi List,

I know this feature ist experimentel but i got a little questions about that.

In the thread "Nagios 3 Performance Monitoring"
Ethan was sugesting to use the this funktion to smooth the the queue.

Know i was wondering some thing about the intervall and window.
The suggestion was an intervall of 60 and an window of 300.
So if the intervall ist shorter thenn the window it seems to be
possible that one or more checks are never checked,
because in every intervall its possible that the always same checks
are rescheduld to  a later time and so are never checked.

In the other case if i have the same intervall and window no check
falls out but so the smoothing effact ist not so high because its
possible that
in every window i have diffrent amounts of checks, f.e 500,1000,100,........

So first i think i will use same value for intervall and window but if
my checkamount is incrising i think
it will be better to get an solution for the the "problem".

So now, did i get it right or did i forget something?

Mark

--
Mark Eisenblätter
Geissendoerfer & Leschinsky GmbH
www.gl-sytemhaus.de



-- 
Mark Eisenblätter
Geissendoerfer & Leschinsky GmbH
www.gl-sytemhaus.de

-------------------------------------------------------------------------
This SF.net email is sponsored by: Microsoft
Defy all challenges. Microsoft(R) Visual Studio 2005.
http://clk.atdmt.com/MRT/go/vse0120000070mrt/direct/01/




More information about the Developers mailing list