Nag 2.x seems to have introduced a new field in the availability report
CGI panel (http://your_nag/nagios/cgi-bin/avail.cgi?... the third panel
that looks like
Service Availability Report
Last Updated: Mon May 16 14:27:55 EST 2005
Nagios - www.nagios.org
Logged in as anwsmh
Step 3: Select Report
Options
Report Period: [Last 7
Days_____________]
If Custom Report Period...
Start Date (Inclusive): [May______] 1_ 2005
End Date (Inclusive): [May______] 16 2005
Report time Period: [None___________]
Assume Initial States: [Yes]
Assume State Retention: [Yes]
Assume States During Program Downtime: [Yes]
Include Soft States: [No_]
First Assumed Service State: [Unspecified_____]
ktracked Archives (To Scan For Initial States): 1_
Create Availability
Report!
)
The new field is 'Report Period' and allows the selection of one of the
configured timeperiods (24x7, none, workhours etc).
What does this 'Report Period' field do ?
Does it mean that availability is only computed for that time period ?
(so that availability for the none time period is always 100% and
availability for the 24x7 time period is always the sum of
the down times/reporting interval * 100).
In other words, that downtime falling outside the time period is ignored
?
If so, this is a great adddition and makes reporting for SLAs feasable.
Yours sincerely.
-------------- next part --------------
An embedded and charset-unspecified text was scrubbed...
Name: disclaimer.txt
URL: <https://www.monitoring-lists.org/archive/users/attachments/20050516/7efbfdbb/attachment.txt>
More information about the Users
mailing list